How long does the regulatory process take?

The time required for federal review and pipeline construction varies depending on the size of the pipeline project. For the Atlantic Sunrise Project, Williams filed an application with FERC on March 31, 2015. The application was approved by FERC in February 2017. Pennsylvania construction began in September 2017.